1. Planning and Design
-
Separate the cable types
-
Power cables (LV/MV), low-voltage/weak current (data, telephone, fiber), control cables.
-
If they will be on the same route, the minimum distances between them and the fire compartments must be defined in the project.
-
-
Create a route plan
-
Clarify existing infrastructures (natural gas, drinking water, sewage, other energy and telecom lines) with maps and excavation permits.
-
As far as possible:
-
A short but accessible route,
-
Avoid risky areas (heavy traffic, heavy loads, chemical environments, high temperatures, flood risk).
-
-
Detail the crossing points in particular (under road, bridge, manhole, building entrance).
-
-
Determine the installation method
-
Direct burial (buried in soil),
-
Inside conduit/duct (HDPE, PVC, steel conduit),
-
Cable trays and ladders, tunnels, galleries.
-
Define protection, depth, fill ratio and drainage requirements for each method.
-
2. Cable and Material Selection
-
Use cables that comply with standards
-
Compliant with the relevant IEC/EN/TSE standard (e.g. IEC 60502 series for power cables, etc.).
-
In indoor areas, prefer halogen-free, low flame spread (LSZH) cables.
-
For outdoor use:
-
UV-resistant, outer sheath resistant to moisture and chemicals,
-
If necessary, armoured cable (against mechanical impacts).
-
-
-
Cross-section and conductor type
-
Current carrying capacity, short-circuit withstand and voltage drop must be calculated.
-
Cu/Al selection, single-core/multi-core, screened or armoured must be according to the project calculations.
-
-
Conduit and duct selection
-
Indoors: PVC or metal conduit; outdoors: HDPE corrugated, steel conduit, etc.
-
Fill ratio should generally not exceed 40% of the conduit cross-section (for future cable additions, heating and pulling ease).
-
Choose conduit/tray size that provides the minimum bending radius specified by the cable manufacturer.
-
3. Site Occupational Safety
-
Risk analysis and permits
-
Written work permits for works such as excavation, confined spaces, work near live systems.
-
The locations of existing lines must be marked and the plans shown on site.
-
-
Isolation and securing of energy (LOTO)
-
If possible, the line should be de-energized.
-
Lockout and tagout (LOTO) must be applied at breakers.
-
Absence of voltage must be checked with appropriate equipment.
-
-
Personal protective equipment
-
Helmet, safety boots, reflective vest,
-
Goggles, work gloves (if necessary insulated gloves),
-
Working at height equipment (fall arresters, etc.) where applicable.
-
-
Site organization
-
Open trenches must be fenced and equipped with barriers and warning signs.
-
For trenches deeper than 1.2 m, use shoring or adequate slope to prevent sidewall collapse.
-
Use suitable scaffolds or ladders for entering and exiting trenches.
-
4. Excavation and Route Implementation (Underground Cables)
These are example values; always refer to local regulations and the project.
-
Depth
-
LV power cables: typically ~0.7–0.8 m,
-
MV cables: typically ≥1.0 m,
-
Data/telephone: typically ≥0.6 m.
-
May be increased depending on the load coming from above.
-
-
Bottom preparation
-
The trench bottom must be cleaned of stones, rubble and sharp objects.
-
Generally, a bedding of about 10 cm of sand or fine material is laid and compacted.
-
-
Distances between cables
-
If there is more than one cable in the same trench:
-
Horizontal and vertical clearances must be as per the project (e.g. at least 20–30 cm between a power cable and a telecom cable).
-
-
At crossings with other infrastructures (natural gas, water, etc.) intersect, aim for 90° crossings where possible.
-
-
Backfilling
-
Place another 10 cm of sand/fine material on top of the cable,
-
Then a warning tape (red – energy, blue – water, etc., according to the utility’s standard),
-
Then backfill with native soil and compact.
-
5. Laying the Cable (Pulling / Laying Out)
-
Cable drum and preparation
-
The cable drum must be upright and locked, and the risk of tipping must be prevented.
-
Check for cuts, crushing or holes on the outer sheath.
-
Ensure that water has not entered the cable, especially at the ends (use temporary caps/insulation on the ends).
-
-
Pulling direction and equipment
-
If possible, position the drum so that the cable is paid out from the bottom of the drum (pulling from the top can bend the cable).
-
For long distances, use rollers / slides along the drum route.
-
For pulling through conduits:
-
Use a suitable pulling rope and pulling head (of a type that will not damage the cable),
-
If necessary, use a winch + dynamometer for pulling force,
-
Use cable pulling lubricant to reduce friction.
-
-
-
Pulling force and bending radius
-
Do not exceed the maximum pulling force specified in the cable manufacturer’s catalogues.
-
Bending radius:
-
Typically minimum 8× outer diameter for unarmoured cable,
-
Minimum 12× outer diameter for armoured cable (varies by cable type – refer to the catalogue).
-
-
Protect the cable from sudden bends/kinks and “sharp elbows”.
-
-
Excess length and slack
-
Leave a certain amount of cable slack at drum transition points (manholes, building entrances, in front of panels).
-
It is invaluable for future joints/modifications.
-
6. Joints and Terminations
-
Qualified personnel required
-
In particular, MV/HV cable joints and terminations must only be carried out by trained and authorized personnel.
-
Original joint and termination kits must be used; “improvised” solutions with similar materials are dangerous.
-
-
Cable preparation
-
During cutting, stripping and removal of screens/armour, do not damage the conductors or insulation.
-
Knife marks and scratches may later cause partial discharge or faults.
-
Work in a clean environment and, if necessary, clean the insulation surface with isopropyl alcohol (according to the manufacturer’s instructions).
-
-
Lug and terminal connections
-
Use cable lugs suitable for the correct cross-section.
-
Crimp with appropriate crimping tools and dies, such as hydraulic presses.
-
For bolted connections, use a torque wrench according to the manufacturer’s torque values.
-
-
Sealing and insulation
-
Apply heat-shrink or cold-shrink sleeves, resin boxes, etc. on joints and terminations according to instructions.
-
Proper shrinking is important to prevent ingress of moisture, water and dust.
-
-
Earthing and screen bonding
-
The earthing points of armour, screens and metallic sheaths must be as per the design:
-
Single-point / double-point earthing,
-
Screen separation systems – these must be implemented according to the project engineer’s decision.
-
-
Connect metal conduits, trays and boxes to the PE bar (equipotential bonding).
-
7. Fixing Cables and Mechanical Protection
-
Cable trays and ladders
-
Determine tray/ladder spacing by checking load capacity (to avoid sagging).
-
In corrosive environments, use galvanized or painted/stainless materials.
-
Secure with regular cable clamps horizontally and vertically; do not overtighten clamps to crush the cable.
-
-
Vertical shafts and risers
-
Cable weight increases in vertical runs, so use cable supports/clamps at certain floors.
-
For large cross-section power cables, use a cable clamp system resistant to short-circuit forces.
-
-
Separation between cables
-
If there are different voltage levels (e.g. 400 V and 24 V) on the same tray, use a divider plate or separate trays.
-
Route power cables and data/fiber cables separately as far as possible; if on the same route, meet spacing and screening requirements.
-
-
Protection at penetrations and openings
-
At wall/tile penetrations, provide mechanical protection with a cable gland/bushing or sleeve conduit.
-
When passing through fire walls, seal gaps with fire-stopping mortar/kit.
-
8. Earthing, Equipotential Bonding and Surge Arresters
-
Continuity of protective conductor
-
All sockets, panels, motors and metal enclosures must be connected to the PE conductor.
-
Trays, metal conduits and junction boxes must be connected to the equipotential bar.
-
-
Lightning protection and surge arresters
-
If the building has a lightning protection system, power cables and metal lines must be designed in harmony with it.
-
Use surge arresters of appropriate class in critical panels (e.g. Type 1 in the main panel, Type 2 in sub-panels, etc., according to the project design).
-
9. Testing, Inspection and Documentation
-
Visual inspection
-
Are there any breaks, dents, sheath damage, wrong routes, missing clamps or loose connections?
-
Check at sample points that the cable is correctly coded and routed.
-
-
Electrical tests
-
Continuity test (phase, neutral, PE),
-
Insulation resistance test (megger): at the relevant voltage level, results must be above the minimum required by standards.
-
If required:
-
High-voltage test (for MV cables),
-
Earth resistance measurement,
-
Short-circuit loop impedance, etc.
-
-
-
For data and fiber cables
-
Certification testing of data cables (with a tester suitable for the category – Cat6, Cat7, etc.),
-
For fiber cables, OTDR and loss measurements.
-
-
Labelling and records
-
Each cable must carry a permanent label at both ends and at intermediate manholes/joint points (e.g. line number, panel it supplies, etc.).
-
Update the “as-built” project:
-
Cable route,
-
Cable type, cross-section, length,
-
Joint and manhole locations,
-
Test reports.
-
-
10. Common Mistakes and Short Prevention Checklist
Avoid:
-
Pulling cables without paying attention to the maximum pulling force and bending radius.
-
Filling the same tray with every voltage level without any separation.
-
Making joints and terminations in unsuitable environments (mud, dust, under rain).
-
Leaving earthing and screen connections “to look at later”.
-
Cutting the cable before making sure twice over that it is the correct cable (!).
Mini checklist:
-
Are routes and depths compliant with the project and regulations?
-
Are cable type, cross-section and protective elements in line with the approved project?
-
Have pulling and bending limits been observed?
-
Are joints and terminations in accordance with instructions, clean and sealed?
-
Are all metal parts and cable armour correctly earthed?
-
Have test reports been taken and archived?
-
Have cable labels and as-built drawings been updated?

