How to Safely Install Cables in Infrastructure Projects?

  • Home
  • Blog
  • How to Safely Install Cables in Infrastructure Projects?
002 Banner

How to Safely Install Cables in Infrastructure Projects?

1. Planning and Design

  1. Separate the cable types

    • Power cables (LV/MV), low-voltage/weak current (data, telephone, fiber), control cables.

    • If they will be on the same route, the minimum distances between them and the fire compartments must be defined in the project.

  2. Create a route plan

    • Clarify existing infrastructures (natural gas, drinking water, sewage, other energy and telecom lines) with maps and excavation permits.

    • As far as possible:

      • A short but accessible route,

      • Avoid risky areas (heavy traffic, heavy loads, chemical environments, high temperatures, flood risk).

    • Detail the crossing points in particular (under road, bridge, manhole, building entrance).

  3. Determine the installation method

    • Direct burial (buried in soil),

    • Inside conduit/duct (HDPE, PVC, steel conduit),

    • Cable trays and ladders, tunnels, galleries.

    • Define protection, depth, fill ratio and drainage requirements for each method.


2. Cable and Material Selection

  1. Use cables that comply with standards

    • Compliant with the relevant IEC/EN/TSE standard (e.g. IEC 60502 series for power cables, etc.).

    • In indoor areas, prefer halogen-free, low flame spread (LSZH) cables.

    • For outdoor use:

      • UV-resistant, outer sheath resistant to moisture and chemicals,

      • If necessary, armoured cable (against mechanical impacts).

  2. Cross-section and conductor type

    • Current carrying capacity, short-circuit withstand and voltage drop must be calculated.

    • Cu/Al selection, single-core/multi-core, screened or armoured must be according to the project calculations.

  3. Conduit and duct selection

    • Indoors: PVC or metal conduit; outdoors: HDPE corrugated, steel conduit, etc.

    • Fill ratio should generally not exceed 40% of the conduit cross-section (for future cable additions, heating and pulling ease).

    • Choose conduit/tray size that provides the minimum bending radius specified by the cable manufacturer.


3. Site Occupational Safety

  1. Risk analysis and permits

    • Written work permits for works such as excavation, confined spaces, work near live systems.

    • The locations of existing lines must be marked and the plans shown on site.

  2. Isolation and securing of energy (LOTO)

    • If possible, the line should be de-energized.

    • Lockout and tagout (LOTO) must be applied at breakers.

    • Absence of voltage must be checked with appropriate equipment.

  3. Personal protective equipment

    • Helmet, safety boots, reflective vest,

    • Goggles, work gloves (if necessary insulated gloves),

    • Working at height equipment (fall arresters, etc.) where applicable.

  4. Site organization

    • Open trenches must be fenced and equipped with barriers and warning signs.

    • For trenches deeper than 1.2 m, use shoring or adequate slope to prevent sidewall collapse.

    • Use suitable scaffolds or ladders for entering and exiting trenches.


4. Excavation and Route Implementation (Underground Cables)

These are example values; always refer to local regulations and the project.

  1. Depth

    • LV power cables: typically ~0.7–0.8 m,

    • MV cables: typically ≥1.0 m,

    • Data/telephone: typically ≥0.6 m.

    • May be increased depending on the load coming from above.

  2. Bottom preparation

    • The trench bottom must be cleaned of stones, rubble and sharp objects.

    • Generally, a bedding of about 10 cm of sand or fine material is laid and compacted.

  3. Distances between cables

    • If there is more than one cable in the same trench:

      • Horizontal and vertical clearances must be as per the project (e.g. at least 20–30 cm between a power cable and a telecom cable).

    • At crossings with other infrastructures (natural gas, water, etc.) intersect, aim for 90° crossings where possible.

  4. Backfilling

    • Place another 10 cm of sand/fine material on top of the cable,

    • Then a warning tape (red – energy, blue – water, etc., according to the utility’s standard),

    • Then backfill with native soil and compact.


5. Laying the Cable (Pulling / Laying Out)

  1. Cable drum and preparation

    • The cable drum must be upright and locked, and the risk of tipping must be prevented.

    • Check for cuts, crushing or holes on the outer sheath.

    • Ensure that water has not entered the cable, especially at the ends (use temporary caps/insulation on the ends).

  2. Pulling direction and equipment

    • If possible, position the drum so that the cable is paid out from the bottom of the drum (pulling from the top can bend the cable).

    • For long distances, use rollers / slides along the drum route.

    • For pulling through conduits:

      • Use a suitable pulling rope and pulling head (of a type that will not damage the cable),

      • If necessary, use a winch + dynamometer for pulling force,

      • Use cable pulling lubricant to reduce friction.

  3. Pulling force and bending radius

    • Do not exceed the maximum pulling force specified in the cable manufacturer’s catalogues.

    • Bending radius:

      • Typically minimum 8× outer diameter for unarmoured cable,

      • Minimum 12× outer diameter for armoured cable (varies by cable type – refer to the catalogue).

    • Protect the cable from sudden bends/kinks and “sharp elbows”.

  4. Excess length and slack

    • Leave a certain amount of cable slack at drum transition points (manholes, building entrances, in front of panels).

    • It is invaluable for future joints/modifications.


6. Joints and Terminations

  1. Qualified personnel required

    • In particular, MV/HV cable joints and terminations must only be carried out by trained and authorized personnel.

    • Original joint and termination kits must be used; “improvised” solutions with similar materials are dangerous.

  2. Cable preparation

    • During cutting, stripping and removal of screens/armour, do not damage the conductors or insulation.

    • Knife marks and scratches may later cause partial discharge or faults.

    • Work in a clean environment and, if necessary, clean the insulation surface with isopropyl alcohol (according to the manufacturer’s instructions).

  3. Lug and terminal connections

    • Use cable lugs suitable for the correct cross-section.

    • Crimp with appropriate crimping tools and dies, such as hydraulic presses.

    • For bolted connections, use a torque wrench according to the manufacturer’s torque values.

  4. Sealing and insulation

    • Apply heat-shrink or cold-shrink sleeves, resin boxes, etc. on joints and terminations according to instructions.

    • Proper shrinking is important to prevent ingress of moisture, water and dust.

  5. Earthing and screen bonding

    • The earthing points of armour, screens and metallic sheaths must be as per the design:

      • Single-point / double-point earthing,

      • Screen separation systems – these must be implemented according to the project engineer’s decision.

    • Connect metal conduits, trays and boxes to the PE bar (equipotential bonding).


7. Fixing Cables and Mechanical Protection

  1. Cable trays and ladders

    • Determine tray/ladder spacing by checking load capacity (to avoid sagging).

    • In corrosive environments, use galvanized or painted/stainless materials.

    • Secure with regular cable clamps horizontally and vertically; do not overtighten clamps to crush the cable.

  2. Vertical shafts and risers

    • Cable weight increases in vertical runs, so use cable supports/clamps at certain floors.

    • For large cross-section power cables, use a cable clamp system resistant to short-circuit forces.

  3. Separation between cables

    • If there are different voltage levels (e.g. 400 V and 24 V) on the same tray, use a divider plate or separate trays.

    • Route power cables and data/fiber cables separately as far as possible; if on the same route, meet spacing and screening requirements.

  4. Protection at penetrations and openings

    • At wall/tile penetrations, provide mechanical protection with a cable gland/bushing or sleeve conduit.

    • When passing through fire walls, seal gaps with fire-stopping mortar/kit.


8. Earthing, Equipotential Bonding and Surge Arresters

  1. Continuity of protective conductor

    • All sockets, panels, motors and metal enclosures must be connected to the PE conductor.

    • Trays, metal conduits and junction boxes must be connected to the equipotential bar.

  2. Lightning protection and surge arresters

    • If the building has a lightning protection system, power cables and metal lines must be designed in harmony with it.

    • Use surge arresters of appropriate class in critical panels (e.g. Type 1 in the main panel, Type 2 in sub-panels, etc., according to the project design).


9. Testing, Inspection and Documentation

  1. Visual inspection

    • Are there any breaks, dents, sheath damage, wrong routes, missing clamps or loose connections?

    • Check at sample points that the cable is correctly coded and routed.

  2. Electrical tests

    • Continuity test (phase, neutral, PE),

    • Insulation resistance test (megger): at the relevant voltage level, results must be above the minimum required by standards.

    • If required:

      • High-voltage test (for MV cables),

      • Earth resistance measurement,

      • Short-circuit loop impedance, etc.

  3. For data and fiber cables

    • Certification testing of data cables (with a tester suitable for the category – Cat6, Cat7, etc.),

    • For fiber cables, OTDR and loss measurements.

  4. Labelling and records

    • Each cable must carry a permanent label at both ends and at intermediate manholes/joint points (e.g. line number, panel it supplies, etc.).

    • Update the “as-built” project:

      • Cable route,

      • Cable type, cross-section, length,

      • Joint and manhole locations,

      • Test reports.


10. Common Mistakes and Short Prevention Checklist

Avoid:

  • Pulling cables without paying attention to the maximum pulling force and bending radius.

  • Filling the same tray with every voltage level without any separation.

  • Making joints and terminations in unsuitable environments (mud, dust, under rain).

  • Leaving earthing and screen connections “to look at later”.

  • Cutting the cable before making sure twice over that it is the correct cable (!).

Mini checklist:

  • Are routes and depths compliant with the project and regulations?

  • Are cable type, cross-section and protective elements in line with the approved project?

  • Have pulling and bending limits been observed?

  • Are joints and terminations in accordance with instructions, clean and sealed?

  • Are all metal parts and cable armour correctly earthed?

  • Have test reports been taken and archived?

  • Have cable labels and as-built drawings been updated?